Project 12: Complete switching substation in LelystadAn extension of the 380 kV substation in Lelystad is planned. Construction of the substation progressed very well in 2008. The upgrade involves installing an additional 380 kV transformer to create a complete switching substation. A new Electrabel power station will be connected to the substation. The new substation will be operational in 2009.
|