Project 4: New substation at Simonshaven


This substation is being built to connect a production unit and link the 150 kV grid to the 380 kV high-voltage grid, and to accommodate new production capacity. The detail engineering work was completed in 2008. After issuing calls for tenders and awarding all the contracts, TenneT started building the substation. It will be commissioned in the third quarter of 2009.

 